Jubilee Line Extension

Project:Jubilee Line Extension
Client:London Underground
Contractor:Balfour Beatty / Amec
Package Value:£2,700,000
Year:1996

Pyramid Builders works on the Jubilee line included the building a new brickwork street elevation at Alaska Street, the complete masonry brick, block and scaffold package at Waterloo station, the full masonry new build and refurbishment package at Westminster Station/Green Park vent shaft.

Waterloo Station in particular required very skilled refurbishment craftsman to restore and build new barrel arches to match and complement the existing.

All work was carried out to accommodate live working London Underground Stations.